Coeur d’Ixelles in Brussels

The project comprises part of the former offices of Electrabel. The offices had been vacant for several years.

The mix (shops, offices, and housing) contributed to the better integration of the project in a neighbourhood that already combined these three functions. The aim of this project was for the most part environmental, which led to the creation of an 8- acre garden and the construction of energy-efficient housing.

The renovation related to the underground level and the office building. The challenge for this building was to maintain its structure while changing its function.

Immo-Pro was tasked with construction project management for the entire project, from the feasibility, the draft project, the construction, the many technical and financial aspects.

 

 

ClientImmo XL
End clientN/A
MissionConstruction project management
Design officesCorbisier & Associés - Setesco - Venac
ContractorLes Entreprises Louis De Waele
Locationchaussée d'Ixelles in 1050 Brussels
Project typePartial demolition of an existing building and construction of new buildings
Building typeHousing (55 apartments)
Offices 600 sq.m.
Shops 641 sq.m.
Parking : 57 underground spaces
Surface area9,800 sq.m.
BEPE 47
Time frame2010 - 2013 (works will last 24 months)
Cost€ 10,500,000