Client | Sfar-Molenblok (Groupe S.R.I.B) |
End Client | Le Foyer Bruxellois |
Mission | Consultant |
Design offices | Antex – MR Engineering – Ellyps |
Contractor | Gillion Construct |
Location | rue du Molenblok in 1120 Brussels |
Project Type | New build |
Type de bâtiment | 28 social housing units + 22 parking spaces |
Surface area | 3,164 sq.m. aboveground |
BEP | Passive |
Period | from 2008 until 2016 |
Cost | € 4,100,000 |
We are working as a technical consultant for SFAR which is building new social housing and amenities in the Brussels-Capital Region.
We are assisting the contracting authority throughout this project, which consists of designating and coordinating the various contractors, including engineering consultancies and companies, as well as following up the project in its entirety, their delivery and transmission to the operators.
The project was initially delayed due to a lack of roads, sewerage connections and contractors. Once these problems had been resolved by the authorities in charge, and after the works contract had been awarded, construction was able to start in 2014. The project comprises 28 social housing units and 22 underground parking spaces. This is a passive building.
The provisional delivery is scheduled in the course of 2016.